Garage Construction Project
Annoucncements v1

December 21, 2012
10 East Ontario Parking Garage Project Recap-ZeraConstruction Co., Inc.


The following tasks were completed week ending December 21, 2012

   1.     Framing and pouring of portions of the full depth repairs for PT work

2.    PT repairs continued on the second floor

3.    Minor partial depth repairs on the third floor.

The following tasks will take place during the week ofDecember 24, 2012

   1.    Concrete and PT repairs to continue on the inner portions of the second floor.
   
2.    Framing and pouring for the remaining pt repairs 
   3.    Portions of the enclosures will be removed on the second floor
   
4.    We will be working on Wednesday-Friday next week only 

Patch framed and ready to pour


Full depth and PTshoring on the ground floor

 

December 14, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending December 14, 2012

 

1.      Demolition of second floor pour strip completed

2.     Second floor slab edge and phase B concrete work completed

3.     Second floor PT repairs continued

 

 

The following tasks will take place during the week of December 17, 2012

 

1.     Concrete and PT repairs to continue on the inner portions of the second floor.

2.     Second floor pour strip will be poured this week


Phase B PT repair


Full depth PT repairs on the second floor


 

December 7, 2012

 

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending December 7, 2012

 

1.      Demolition of second floor pour strip started

 

2.     Second floor slab edge and phase B concrete work started

 

3.     Second floor PT repairs were revealed and started

 

4.     Third floor enclosures were removed

 

5.     Plumbing rodding and change order work continued

 

 

The following tasks will take place during the week of December 10, 2012

 

1.     Concrete and PT repairs to continue on the inner portions of the second floor.

 

2.     PT repairs will continue on the second floor

 

3.     Second floor pour strip will be poured by the end of the week

Phase B slab edge second floor

Dust enclosure floor on

e

 


 
November 23, 2012
10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.


The following tasks were completed week ending November 23,  2012

   1.      The fourth floor inner portion of the pour strip was stripped and cleaned up.
   
   
2.     Dust partitions were erected on the inner portion of the second floor.

   
3.     Demolition and framing started on the inner portion of the third floor pour strip.

   
4.     Plumbing and drain rodding took place throughout the garage. 

5.     The fourth floor inner portion of the pour strip will be poured on Friday 11/16/12


The following tasks will take place during the week of November 26, 2012

   1.     Concrete and PT repairs to continue on the inner portions of the lower floors
   
   
2.     Pour the inner portion of the third floor pour strip

   
3.      Dust partitions will be erected on the inner portions of the first floor

   
4.     Phase B slab edge repairs will be framed and poured.

Phase B slab edge third floor

 



Fourth floor pour strip being stripped and cleaned up
 


 


November 15, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

 

The following tasks were completed week ending November 16,  2012

 

 

1.       All outer portions of the pour strips and concrete repairs are complete

 

2.     Painting of the Wabash portions of the commercial floors is complete

 

3.     Concrete and pt repairs continued on the lower floors

 

4.     Demolition continued on the inner portions of the fourth floor pour strip

 

5.     The fourth floor inner portion of the pour strip will be poured on Friday 11/16/12

 

 

The following tasks will take place during the week of November 19, 2012

 

1.     Concrete and PT repairs to continue on the inner portions of the lower floors

2.     Pour strip demolition will begin on the third floor

 

3.      Dust partitions will be erected on the inner portions of the second floor

Phase B center enclosure third floor

                  First floor PT lock off

               


 

 

November 2, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

 

The following tasks were completed week ending November 2,  2012

 

   1.       Pour strip (outer portions) on the third floor were poured

 

2.     Painting preparation was completed on outer portions of the commercial floors.

 

3.     Concrete and pt repairs continued on the first floor

 

4.     Demolition began on the outer portion of the second floor pour strip

 

 

The following tasks will take place during the week of November 5, 2012

 

1.     Concrete and PT repairs to continue on the lower floors

2.     Pour portions of the pour strip on the second floor

 

3.     Painting will start on portions of floors 4-1

PT lock offs third floor



         First floor pour strip enclosure being erected





 

October 25, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending October 26, 2012

 

1.     Pour strip (outer portions) on the fourth floor were poured

 

2.     Painting preparation started on outer portions of the commercial floors.

 

3.     Concrete and pt repairs continued on the first floor

 

 

The following tasks will take place during the week of November 2, 2012

 

1.     Concrete and PT repairs to continue on the lower floors

2.     Pour portions of the pour strip on the third floor

 

3.     Painting preparation on portions of floors 4-1 will continue

Fourth floor pour strip enclosure



Third floor pour strip enclosure



 

 

October 12, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending October 12, 2012

   1.     Finished painting on all residential floors
   
2.     Membrane completed on all residential floors
   
3.     Striping completed on floors 9-6
   
4.     Concrete repairs on lower floors continued

The following tasks will take place during the week of October 15, 2012

   1.     Striping completed on the 5th floor (Monday)
   
2.     Cleanup of the residential floors (Monday)
   
3.     Residential floors opened for parking (Monday PM)
   
4.     Concrete and PT repairs to continue on the lower floors

Drive aisles on the 5th floor


9th Floor completed with striping



 

October 4, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending October 5, 2012

 

1.     Finished painting 7 and 6, started 5

2.     Concrete and PT repairs continued on phase B lower floor areas

3.     Membrane complete on floors 9 and 8

4.     Preparation and caulking completed on floors 7 and 6

 

 

The following tasks will take place during the week of October 8, 2012

 

1.     Painting to complete on floor 5

2.     Shot blasting and caulking floor 5.

3.     Membrane installations complete all floors.

4.     Striping to begin

Base coat on the 8th floor



 

Topcoat being applied to the 9th floor






 




Ontario Place

Condominium Association

10 East Ontario

Chicago, Illinois 60611

(312) 337-5722 / Fax (312) 664-3128

www.ontarioplace-condo.com

September 26, 2012   

                *IMPORTANT NOTIFICATION*

                                                                       

Ontario Place Condominium Association      

10 East Ontario

Chicago, Illinois 60611                                  

 

RE: GARAGE RENOVATION PROJECT

           

Dear Unit Owner, Resident, Garage Parker of Ontario Place:

 

Residential Parkers (parking spaces on floors 5-9) will be able to begin parking in their parking space as of MONDAY, OCTOBER 15, 2012 after 5:00PM. Transponders will be turned on as of this time to allow re-entry into the garage.

 

The project will continue on the lower levels of the garage. Therefore, you should still anticipate dust, noise, and traffic configurations through the garage on the lower floors.

 

The representatives at the following garages have been informed that parkers will be giving notice to vacate as of MONDAY, OCTOBER 15, 2012 after 5:00pm.

 

50 East Ohio

10 East Grand

540 N. State Street

 

Please be sure to contact the garage you are parking in to notify them of your intention to vacate as of 10/15/12. You will need to follow whatever directions they provide you regarding procedures for returning access cards, etc.

 

The Association would like to thank everyone for their cooperation and understanding as we realize that this project has been very disruptive and inconvenient. Management will continue to post project updates on the Association’s website: www.ontarioplace-condo.com. (You may click on the “Garage Construction Project” link located on the left side of the home page.) 

 

Once again, thank you for your support and understanding during this project. If you have any questions, please feel free to contact the Management Office at 312-337-5722 or via email at ontarioplace@sudlerchicago.com

 

Sincerely,

The Private Residences at Ontario Place Condominium Association

 

 

 

Marci Weiner, CMCA

Condominium Property Manager

Sudler Property Management

 

 


September 21, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

 

The following tasks were completed week ending September 21, 2012

 

 

1.       9th Floor ceiling painting complete, 8th floor 50%

 

2.     Painting preparation on floors 9-6 90% complete

 

3.     Concrete and PT repairs continued on phase B lower floor areas

 

4.     Z Panels complete down to the third floor on Wabash

 

5.     Corner scaffolding and sign removed

 

 

The following tasks will take place during the week of September 28, 2012

 

1.     Painting to continue on 8 and moving down.

 

2.     Shot blasting and caulking will be completed on floors 9 and 8 in preparation for membrane

 

3.     Z panels installation will continue Wabash will begin on floors 3 and down

 

4.     Pour strip repairs will continue on the commercial floors


Pour Strip poured on the 5th Floor 



Painted ceiling (sorry kind of close)


 


September 14, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

 

The following tasks were completed week ending September 14, 2012

 

 

1.       Phase A slab edge framing continued on Wabash street first floor

 

2.     Uniform PT repairs completed on 2nd floor phase A.

 

3.     Painting preparation continued on the 8th and 7th.

 

4.     Pour strip on the 5th floor was poured.

 

5.     Membrane surface preparation began on the top floors

 

 

The following tasks will take place during the week of September 17, 2012

 

1.     Phase A Wabash slab edges prep and framing will continue on the lower floors

 

2.     Uniform PT repairs will continue on phase A Wabash Street lower floors

 

3.     Concrete repairs will continue on Wabash Street slab edge lower levels and concrete repairs will continue on the phase b lower floors

 

4.     Z panels installation will continue Wabash will begin on floors 6 and 5

 

5.     Painting and membrane preparation will continue on lower floors

 

6.     Pour strip repairs will continue on the commercial floors

 

7.     Painting will begin on the upper floors

Pour Strip 5th Floor




Slab edge first floor



 

September 7, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending September 7, 2012 

1.      Phase A concrete poured on Wabash floor 3 and 2. 

2.      Phase A slab edge framing continued on Wabash street lower floors 

3.     Uniform PT repairs completed on 3rd floor phase A. 

4.     Painting preparation continued on the 9th and 8th floors. 

5.     Pour strip on the 5th floor was framed and prepared.
 

The following tasks will take place during the week of September 4, 2012 

1.     Phase A Wabash slab edges prep and framing will continue on the lower floors 

2.     Uniform PT repairs will continue on phase A Wabash Street floor2 

3.     Concrete repairs will continue on Wabash Street slab edge lower levels and concrete repairs will continue on the phase b lower floors 

4.     Z panels installation will continue Wabash will begin on floors 8 and 7

5.     Painting and membrane preparation will continue on 8 and move down to the 7th floor 

6.     Pour strip repairs will continue on the commercial floors


Slab edge poured and stripped






Full depth framing phaseB



 

August 31, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending August 31, 2012
   
   
1.      Phase A concrete poured on Wabash floor 4.
   
2.      Phase A slab edge framing continued on Wabash street lower floors
   
3.     Uniform PT repairs completed on 4for phase A tendon repairs at Wabash slab edge. 
         Floor three is locked off.
   
4.     75% of painting preparation completed on the 9th floor
   
5.     Pour strip on floor 9 was poured and the 5th floor pour strip was demolished.

 The following tasks will take place during the week of September 4, 2012

    1.     Phase A Wabash slab edges prep and framing will continue on the lower floors
   
2.     Uniform PT repairs will continue on phase A Wabash Street floors 3 and 2
   
3.     Concrete repairs will continue on Wabash Street slab edge lower levels and concrete repairs will continue on the phase b lower floors
   
4.     Z panels installation will continue Wabash will begin on floors 8 and 7
   
5.     Painting and membrane preparation will continue on 9 and move down to the 8th floor
   
6.     Pour strip repairs will begin on the commercial floors

 

PT Lock offs on the third floor

 


 

 

Painting preparation 9th floor





 

 

August 10, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending August 10, 2012

1.     Phase A concrete poured on Wabash floor 9

2.     Phase A slab edge framing continued on Wabash street upper floors

3.    Uniform PT repairs began for phase A tendon repairs at Wabash slab edge

4.    Sidewalk canopy was removed from the majority of Ontario Street.

The following tasks will take place during the week of August 13, 2012

1.    Phase A Wabash slab edges will be poured on floors 8 and 7

2.    Uniform PT repairs will continue on phase A Wabash Street

3.    Concrete repairs will continue on Wabash Street slab edge lower levels

4.    Z panels will be installed on Wabash floors 9 and 8

 Shoring on Wabash Street


Prepared and framed slab edge ready to pour  

 


July 20, 2012

 

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 The following tasks were completed week ending July 20, 2012

1.     Phase B concrete repairs on floors 5 and 6 continued

2.     Z panel removal complete on Wabash street

3.     Scaffold removal began on Ontario Street

4.    7th floor pour strip was prepared and framed   

 The following tasks will take place during the week of July 23, 2012

1.    Z panel restoration will begin on Wabash pieces

2.    Scaffold on Ontario will be 100% removed

3.    Phase A Ontario partition walls will begin to come down

4.    Concrete repairs will continue on Wabash Street slab edge

5.    Uniformed PT repairs will continue in phase B

 Wabash slab edge prepared for pouring


July 13, 2012

 

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending July 13, 2012

1.     Phase B concrete repairs on floors 5 and 6 continued

2.     Z panel removal began on Wabash street

3.     11 PT cables were repaired at the alley wall

4.    6th floor pour strip was poured   

 The following tasks will take place during the week of July 16, 2012

1.    Z panel removal will continue on Wabash

2.    Scaffold on Ontario will begin to be removed

3.    Phase B concrete will be poured on the 5th floor

4.    Concrete repairs will continue on Wabash Street slab edge

5.    Uniformed PT repairs will continue in phase B

 Pour strip sandblasted prior to framing and pouring

 


June 29, 2012

 

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending June 21, 2012

1.     Shoring was installed in the alley for PT repairs

2.     Z panel installation was completed on floors 7 and 6

3.     Membrane at slab edge was completed on Ontario Street

4.    Concrete repairs started on Wabash Street

5.    Temporary protection was installed on Wabash Street

The following tasks will take place during the week of June 25, 2012

1.    Z panel re installation will begin on the lower floors

2.    PT repairs at the alley will begin

3.    Z panel removal will begin on Wabash Street

4.    Concrete repairs will continue on Wabash Street and all of the upper levels

 Slab edge repairs on Wabash Street


June 21, 2012

 

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.


The following tasks were completed week ending June 21, 2012

1.     Uniform PT repairs on lower floors continued

2.    Scaffold was completed for phase one on Wabash Street

3.    Sign relocated to scaffolding

4.    Z panels are being restored and patched

5.    Membrane installation on the floors 4 and 3

6.    Z panel re installation 75% complete on floors 7 and 6

 The following tasks will take place during the week of June 25, 2012

1.    Z panel re installation will complete on 7 and 6 and start on 5, 4 and 3

2.    Uniform PT repairs will continue on the lower floors

3.    Membrane installation will continue on floors 5 and 4.

4.    Wabash St. protection will begin as well as upper floor shut downs

Slab edge repairs after forms are removed
 

Z panels being stocked for installation


June 15, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending June 15, 2012

1.    PT repairs 95% complete on the Ontario elevation

2.   Canopy and scaffold erected on Wabash Street

3.   Sign channel restoration completed

4.   Z panels are being restored and patched

5.   Membrane installation on the floors 7, 6, 5 and 4

6.   Z panel re installation continued on floors 7 and 6

 The following tasks will take place during the week of June 18, 2012

1.   Z panel re installation will continue  on lower floors

2.   Additional PT repairs will continue on the lower floors

3.   Membrane preparation will begin on floors 5 and 4.

4.   Scaffold will be removed on floors 9 and 8 on the Ontario elevation.

Slab edge uniform pt tendon repair
 


June 1, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending June 1, 2012

1.     PT repair areas poured on floors 7 and 6

2.    Several more Post tension cables in the process of being repaired on the lower floors

3.    Z panels are being restored and patched

4.    Membrane preparation on floors 7 and 6

5.    Z panel re installation 75% complete on floors 9 and 8

 The following tasks will take place during the week of June 4, 2012

1.    Z panel re installation will continue on floors 9 and 8 and begin on 7 and 6

2.    Additional PT repairs will continue on the lower floors

3.    Membrane installation will begin on floors 7 and 6.

PT cables under repair

Slab edge membrane with restored and repainted angles

May 18, 2012

 10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

 The following tasks were completed week ending May 18, 2012

 

 1.      Slab edges poured on floors 5 and 4
 2.     28 Post tension repairs Completed on floors 6, 5 and 4
 3.     Z panels are being restored and patched
 4.     Framing continued floors 4, 3 and 2

The following tasks will take place during the week of May 21, 2012

           1.     PT cables will be tensioned on floors 5 and 4
           2.     Additional PT repairs will begin on the lower floors
           3.     PT shoring will be erected on the East portion of the garage starting
                Wednesday.

PT Couplers installed on the 7th floor


PT end anchors installed on the 8th floor  


 

May 3, 2012
10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending May 4, 2012

1.      Slab edges poured on floors 9 and 8
2.     Post tension repairs started on floors 8, 7 and 6
3.     Z panels are being restored and patched
4.     Framing continued on all floors 

The following tasks will take place during the week of May 7, 2012

1.     PT cables will be tensioned on floors 8 and 7
2.     Additional PT repairs will begin on the lower floors
3.     Column and slab edge pouring will continue
4.     Steel angle painting will continue

Poured slab edge on the 9th floor


PT shoring in place  


 

April 20, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc. 

 

The following tasks were completed week ending April 20, 2012 

 

1.      Concrete repair demolition continued 

2.     Post tension repairs were identified and prepared for repairs to begin 4/30/12 

3.     Z panels are being restored and patched 

 

The following tasks will take place during the week of April 23, 2012

 

1.     Concrete demolition will continue on lower floors 

2.     Z panels restoration will continue  

3.     Column patch repair and pouring will continue 

4.     Post tension preparation will continue  

5.     Steel angle painting will continue


Full depth concrete repair




Columns prepared and framed, ready to pour  


 

April 13, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending April 13, 2012

 

1.      Concrete repair demolition continued

 

2.     Post tension repairs were identified for repairs

 

3.     Z panels are being restored and patched

 

The following tasks will take place during the week of April 16, 2012

 

1.     Concrete demolition will continue on lower floors

 

2.      Portions of the concrete repairs will be poured back-West portions of floors 9 and 8

3.     Z panels restoration will continue

 

4.     Column patch repair and pouring will continue

Full depth concrete repair



Columns prepared and framed, ready to pour  

 

April 5, 2012

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.


The following tasks were completed week ending April 6, 2012

 

1.      Z panels were 100% removed on Ontario Street

2.     Concrete repair demolition was completed on portions of the upper floors

3.     Concrete repair demolition continued on the lower floors

4.     All Guard rails were removed on the floors

5.     Post tension repairs were starting to be evaluated on the upper floors

 

The following tasks will take place during the week of April 9, 2012

 

1.     Concrete demolition will continue on all floors

2.    Portions of the concrete repairs will be poured back-West portions of floors 9 and 8

3.     Z panels restoration will begin

4.     Steel angles for Z panels will be prepared and painted for the upper floors


Concrete demolition in progress on the 8th floor

Completed patch demolition on the 9th floor



 

The following tasks were completed week ending May 18, 2012


June 1, 2012
10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending March 23, 2012

      
1.     Pedestrian canopy installed on Ontario  
      2.      50% of scaffolding was installed on Ontario
      3.    
Dust partitions were installed on floors 1-4
 
     4.     Z panels were removed on portions of the Ontario elevation
      5.     Concrete repairs started on floors 1-4

The following tasks will take place during the week of March 26, 2012

      
1.     Remainder of the scaffolding will be erected on the east portion of the pedestrian canopy
      2.     30’ of canopy will be added to Wabash Street 
      3.     Dust partitions will be erected on floors 5-9 
      4.     Z panels will continue to be removed and concrete demo will continue


Sidewalk canopy and Scaffold installed on the Ontario elevation. Portions of the Z panels removed on the lower floors


Z Panel removal and concrete repairs on the second floor

 

2-15-2012
Garage Project:

As we get ready to approach the spring, the Board, management office, contractors and engineers are preparing for the re-start of the Garage Project. The project is anticipated to begin approximately mid-March. The work will be performed in sections around the garage. When construction is being performed in a specific area of the garage, parkers will be required to arrange for alternate parking during the time their parking space is in the construction area. No more that 150 parking stalls will be taken out of use at one time. Management will try and provide an approximate two-week written notification to individual unit owners/parkers informing of the time frame that their parking space will be effected. In an effort to assist with finding alternate parking, Management will be communicating with CPS Parking to negotiate possible reduced parking in some of their nearby garages. 

 

 

November 18, 2011
10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

The following tasks were completed week ending November 18, 2011

1.     All slab edge formwork was removed. 

2.      All shoring was removed and returned to Safway.

3.     Membrane preparation began on the top floors.

4.     Steel angles were all sandblasted and we began priming of the angles.

5.     Guardrail post layout began on the upper floors. 

 The following tasks will take place during the week of November 21, 2011

             1.     Membrane preparation will continue on all floors.
             
            2.     Membrane will be installed on all floors. This will include the slab edge and a 24” 
                  band in the work area. 

 3.     Guardrail post layout will continue.

             4.     Steel angles will all be primed and painted.

Repaired PT tendons prior to the concrete pour


Slab edge poured and stripped after tendons were stressed



 

November 4, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending November 4, 2011

 

1.     PT slab edges were poured and stressed on floors 8 and 9. 

 

2.      Shoring on floors 1-4 was installed.

 

3.     PT Repairs started on floors 3 and 4. 

 

The following tasks will take place during the week of November 7, 2011

 

1.     PT repairs will be completed on floors 3 and 4.

 

2.     Shoring on floors 5 thru 8 will start to be removed.

 

3.     Slab edge embeds will be installed and the remaining slab edges will be framed and poured.

 

October 28, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending October 28, 2011

 

1.     PT repairs started on floors 8 and 9. A total of 8 new tendons were repaired. New splice couplers were installed, tendon and end anchors.

 

2.      Slab edges on floors 8 and 9 were framed and made ready to pour.

 

3.     Investigation work on the uniform tendon pour strip was started.

 

4.     Shoring on floors 1 thru 4 started. 

 

The following tasks will take place during the week of November 4, 2011

 

1.     PT slab edges will be poured and new tendons will be stressed.

 

2.     Shoring on floors 1 thru 4 will be completed.

 

3.     Shoring on floors 5 thru 8 will start to be removed.

 

4.     PT repairs will begin on floors 3 and 4.  


 

New splice couplers and tendons




New live end anchors and edge form



 



October 21, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending October 21, 2011

1.     Shoring was installed on floors 5 through 8.

2.     Investigation/repair holes were created for the post tension (pt) repairs.

The following tasks will take place during the week of October 24, 2011


1.    
 PT repairs will begin on floors 8 and 9.
2.     Concrete repairs for PT work will be ongoing.

Eighth floor Shoring



PT investigation holes


 

 

March 23, 2013
10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

October 14, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.


The following tasks were completed week ending October 14, 2011

1.    
Shoring materials were delivered for PT repairs

2.      Exterior “Z” panels that skin the building were cleaned, filled and patched.

3.     This was a quiet week waiting on shoring materials and parking notifications to expire. (no new photos)

The following tasks will take place during the week of October 17, 2011

1.      Shoring will be erected on floors 5 through 8.

2.     PT end anchors will be chipped, exposed and prepared.

3.     PT subcontractor will mobilize and prepare for repairs.

 


October 6, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending October 7, 2011

 

1.     Slab edge and column preparation and forming.

 

2.      Column concrete patches were poured. 

 

3.      Preparations for the pt repairs began. Shoring designs were completed.

 

4.      Exterior “Z” panels that skin the building were cleaned, filled and patched.

 

The following tasks will take place during the week of October 10, 2011

 

1.      Shoring will be delivered and portions will be erected in the public parking areas.

 

2.     PT end anchors will be chipped, exposed and prepared.

 

3.     PT investigation openings will be completed.

 

4.     PT subcontractor will mobilize and prepare for repairs.

         Photo 1 (Prepared and formed slab edge)




 Photo 2 (Poured column with forming removed)

 

 

 



 

September 29, 2011

10 East Ontario Parking Garage Project Recap-Zera Construction Co., Inc.

 

The following tasks were completed week ending September 30, 2011

1.      Investigation holes we created in the concrete slab to determine where the post tension (pt) cables were located. These holes will also identify how the pt cables will be tied off for future concrete repairs. See photo 1 on page 2.

 
2.      PT subcontractor selection and repair types were determined.

3.      All of the slab edge and column concrete demolition was performed in the trial area. In addition preparation and forming has begun on a portion of these repairs. See photo 2 on page 2 for the concrete demolition.

4.     Portions of the column in the trial area were poured.

5.     The exterior “Z” panels that skin the garage are being cleaned, filled and patched at an offsite location.

 

The following tasks will take place during the week of October 3, 2011

1.     Slab edge and column preparation and forming will continue.

2.    
 Slab edge and column concrete patches will be poured. 

3.      Preparations for the pt repairs will begin, including shoring design and pt repair opening holes.

4.    
 Exterior “Z” panels that skin the building will continue to be cleaned, filled and patched.

 

 

Page 2

Photo 1 (Post tension band investigation hole to determine repair type)



Photo 2 (Slab edge and column demolition trial area)


 
 